June 3rd Winding down, we hosted lunch with the crew from Comfort, the hired building company. They’ve been very gracious & helpful in interacting with the team that has been here to help build. These are the foundation hole prepared for cement for the 8, […]
June 2nd Finished the pit for the septic tank! Sasha is thrilled Done! The hired company is going to begin putting on the top – reinforced cement